building additions
22,726 sf
bridge cranes
5 ea. | 50-ton
Project Details
Phase 3 included a Machine Shop extension and a Fabrication Shop extension, consisting of approximately 22,726 SF of new building additions attached on two ends of the Phase 2 project that was completed by MEB. The facility additions consist of a pre-engineered metal building (PEMB) constructed with a concrete floor slab on piling. The new fabrication shop for phase 3 was designed and constructed to support two 50-ton bridge cranes with limit of one 50-ton bridge crane per bay. The new machine shop for phase 3 was designed and constructed to support three 50-ton bridge cranes with limit of one 50-ton bridge crane per bay. Jib cranes, lathes, cutting machines, and modular offices and bathrooms were installed.