Ovivo Digester Sludge Mixers
5
Concrete Tank Roofs
3 with a 90' diameter
Project Details
Upgrades to the primary digesters including demolition and replacement of three concrete covers, four new tank coating systems, five new mixing systems, miscellaneous concrete repairs, new instrumentation, piping and valving modification and improvements to the digester control system. Minor thickening improvements include new sludge piping and valving in the dissolved air flotation building and new sludge yard piping to the adjacent blend tank.
John Thornton
Senior Project Manager